Pilipinas Property Preview
Why RENT if YOU CAN OWN? No Downpayment Condo in Prime Locations
Real Estate 101 Condo Living by Philippine Property
Life in a condo is like somebody is always looking after your well being, by making sure you are satisfied with your living conditions. Of course, condo staff knows you partly pay for their salaries, so they’ll try to give you, your money’s worth and make you feel like royalty.
Empire East to launch 4,700 residential units in first half
MANILA, Philippines - Empire East Land Holdings Inc., the middle-income residential property arm of tycoon Andrew Tan, will launch 4,700 residential units in the first half this year with an estimated sales value of P12 billion.
“Our confidence level in the real estate sector is very high. Our new projects will enable Filipino families to own quality, budget-friendly homes in the very best locations,” said Anthony Charlemagne Yu, president of Empire East.
The units will come from new projects which include The Rochester in Pasig City, The Sonoma in Sta. Rosa, Laguna and Kasara Resort Towers located near C-5 Road in Bagong Ugong, Pasig City.
Others will come from new phases in ongoing projects across Metro Manila – Green Club Towers in Little Baguio Terraces, Maple Heights in Pioneer Woodlands, Madison Plaza Towers in San Lorenzo Place and Central Park in Cambridge Village.
Kasara marks Empire East’s venture into urban residential resort development, with nearly 2,000 residential units in a nature-filled setting with landscaped greenery, various water features and wide, open spaces.
Empire East is the developer of the successful Laguna BelAir township in the South and several residential condominium and transit-oriented communities in Metro Manila.
“Kasara Resort Towers will offer a modern and relaxing resort lifestyle to middle-income Filipino families,” Yu said.
The project’s recreational deck is fully landscaped with palm trees and tropical plants. The swimming pool complex boasts white beach sand, and features a multipurpose hall at the very center.
Other amenities include a beach volleyball court, basketball court, tennis court, sunken bar and gym.
I am super excited about this, KUDOS Empire East Land Holdings and Megaworld Corp.!
Project Information Consruction Update February 2011
Little Baguio
Over all project accomplishment for Tower 4 is 45%
Tower 4 - Concreting work is substantially complete. On-going works includes pre-cast wall installation, roughing-ins of electric pipes, pipe sleeving works for plumbing and fire protection lines, and installation of exhaust duct riser and civil works such as formworks, scaffolding and rebar installation.
Tower 1 - Excavation works are substantially complete.
Cambridge Village
Over all projects accomplishments for Cluster 1- 28 is 79.55%
Cluster 21 - Turnover of units is on progress.
Cluster 22 and 23 - Preparation of units for turnover at lower levels is now on-going
Cluster 24 - Topped-off already
Cluster 25 & 26 - Started concreting works
Cluster 27-35 - Foundation works is on-going
Turnover Update
Cluster 11-21 Completed
Cluster 22 - 23 On - going turnover
Acceptance Rate - 79.46%
Occupancy Rate - 43.98%
Manhattan Parkway Residences
Overall project accomplishment is 77.70%
All towers are topped-off already at roof deck.
Tower 1 - On-going works includes electrical wiring and devices installation of plumbing fixtures, kitchen cabinets and lavatory counter top and punch listing on some of architectural finishing works.
Tower 2 - Installation of kitchen cabinets and lavatory counter top is on-going
Tower 2 and 3 - on-going works includes electrical wiring and roughing-ins, storm, sanitary, and waterline pipe laying, installation of exhaust duct riser, elevator works and installation of aluminum window frames and glass, and cladding works water proofing and tile works.
Tower 3 - Interior plastering
All Towers - painting and punchlisting for masonry works are also in progress.
Manhattan Garden City - Parkview
Overall project accomplishment is 25.50%
Tower 1 and 2 - Concreting at some parts of basements and podium levels is on progress. On-going works includes roughing-ins and pipe sleeving for electrical and plumbing , CHB laying, plastering and civil works such as formworks, scaffolding, rebar installation.
Tower - Topped-off already
Tower 2 - Concreting works is on-going at 27/F level
Tower 3 Concreting work is on-going at basement level.
Over all project accomplishment for Tower 4 is 45%
Tower 4 - Concreting work is substantially complete. On-going works includes pre-cast wall installation, roughing-ins of electric pipes, pipe sleeving works for plumbing and fire protection lines, and installation of exhaust duct riser and civil works such as formworks, scaffolding and rebar installation.
Tower 1 - Excavation works are substantially complete.
Cambridge Village
Over all projects accomplishments for Cluster 1- 28 is 79.55%
Cluster 21 - Turnover of units is on progress.
Cluster 22 and 23 - Preparation of units for turnover at lower levels is now on-going
Cluster 24 - Topped-off already
Cluster 25 & 26 - Started concreting works
Cluster 27-35 - Foundation works is on-going
Turnover Update
Cluster 11-21 Completed
Cluster 22 - 23 On - going turnover
Acceptance Rate - 79.46%
Occupancy Rate - 43.98%
Manhattan Parkway Residences
Overall project accomplishment is 77.70%
All towers are topped-off already at roof deck.
Tower 1 - On-going works includes electrical wiring and devices installation of plumbing fixtures, kitchen cabinets and lavatory counter top and punch listing on some of architectural finishing works.
Tower 2 - Installation of kitchen cabinets and lavatory counter top is on-going
Tower 2 and 3 - on-going works includes electrical wiring and roughing-ins, storm, sanitary, and waterline pipe laying, installation of exhaust duct riser, elevator works and installation of aluminum window frames and glass, and cladding works water proofing and tile works.
Tower 3 - Interior plastering
All Towers - painting and punchlisting for masonry works are also in progress.
Manhattan Garden City - Parkview
Overall project accomplishment is 25.50%
Tower 1 and 2 - Concreting at some parts of basements and podium levels is on progress. On-going works includes roughing-ins and pipe sleeving for electrical and plumbing , CHB laying, plastering and civil works such as formworks, scaffolding, rebar installation.
Tower - Topped-off already
Tower 2 - Concreting works is on-going at 27/F level
Tower 3 Concreting work is on-going at basement level.
No Place like Manila, Philippines
Come home to Manila!Maraming beses na kitang nilayasan
Iniwanan at ibang pinuntahan
Parang babaeng mahirap talagang malimutan
Ikaw lamang ang aking laging binabalikan
Hinahanap-hanap kita, Manila
Ang ingay mong kay sarap sa tenga
NO DOWNPAYMENT CONDO in MANILA
For more complete details of Price Terms please contact the information below:
Mobile Number: +639182117989
Email Address marylyn.ibiernas@gmail.com
Yahoo Messenger Account marylynibiernas@yahoo.com
Skype Account lynibiernas
Facebook Chat Kindly "Like" Pilipinas Property Preview
We value your time and we are happy to serve you!
God Bless Us All.
Subscribe to:
Posts (Atom)