Little Baguio
Over all project accomplishment for Tower 4 is 45%
Tower 4 - Concreting work is substantially complete. On-going works includes pre-cast wall installation, roughing-ins of electric pipes, pipe sleeving works for plumbing and fire protection lines, and installation of exhaust duct riser and civil works such as formworks, scaffolding and rebar installation.
Tower 1 - Excavation works are substantially complete.
Cambridge Village
Over all projects accomplishments for Cluster 1- 28 is 79.55%
Cluster 21 - Turnover of units is on progress.
Cluster 22 and 23 - Preparation of units for turnover at lower levels is now on-going
Cluster 24 - Topped-off already
Cluster 25 & 26 - Started concreting works
Cluster 27-35 - Foundation works is on-going
Turnover Update
Cluster 11-21 Completed
Cluster 22 - 23 On - going turnover
Acceptance Rate - 79.46%
Occupancy Rate - 43.98%
Manhattan Parkway Residences
Overall project accomplishment is 77.70%
All towers are topped-off already at roof deck.
Tower 1 - On-going works includes electrical wiring and devices installation of plumbing fixtures, kitchen cabinets and lavatory counter top and punch listing on some of architectural finishing works.
Tower 2 - Installation of kitchen cabinets and lavatory counter top is on-going
Tower 2 and 3 - on-going works includes electrical wiring and roughing-ins, storm, sanitary, and waterline pipe laying, installation of exhaust duct riser, elevator works and installation of aluminum window frames and glass, and cladding works water proofing and tile works.
Tower 3 - Interior plastering
All Towers - painting and punchlisting for masonry works are also in progress.
Manhattan Garden City - Parkview
Overall project accomplishment is 25.50%
Tower 1 and 2 - Concreting at some parts of basements and podium levels is on progress. On-going works includes roughing-ins and pipe sleeving for electrical and plumbing , CHB laying, plastering and civil works such as formworks, scaffolding, rebar installation.
Tower - Topped-off already
Tower 2 - Concreting works is on-going at 27/F level
Tower 3 Concreting work is on-going at basement level.